Question: Activity predecessor duration (days) A - 5 B - 3 C - 8 D A 9 E B 4 F C 7 G D 6

Activity

predecessor

duration (days)

A

-

5

B

-

3

C

-

8

D

A

9

E

B

4

F

C

7

G

D

6

H

E, F

2

Draw network diagram nodes. Find critical path.

Please solve clearly so that I can understand easily.