Question: Activity | Predecessor | Duration (weeks) A|-12 B|-14 C|A|3 D|B|6 E|B|5 F|C, D | 4 G|E, FI7 What is the critical path of the project,

Activity | Predecessor | Duration (weeks) A|-12 B|-14 C|A|3 D|B|6 E|B|5 F|C, D | 4 G|E, FI7 What is the critical path of the project, and how long will it take to complete?