Question: Activity Predecessor Duration (weeks) Start A B C D E End -----Start Start Start A C B, D, E ---6 7 7 2 4 ----
Activity Predecessor Duration (weeks) Start A B C D E End -----Start Start Start A C B, D, E ---6 7 7 2 4 ---- Original Activity Cost $ $ $ $ $ ---6,000 7,000 12,000 13,000 8,000 ---- Maximum Allowable Crash Duration (weeks) ---1 2 3 1 1 ---- Crash Costs per Week ---$ 1,750 $ 1,355 $ 750 $ 1,500 $ 3,250