Question: Activity Predecessor Normal Duration Exedited Duration Normal Cost ($1000) Expedited Cost ($1000) A 10 7 31 34 B 4 2 22 25 C B 7
| Activity | Predecessor | Normal Duration | Exedited Duration | Normal Cost ($1000) | Expedited Cost ($1000) |
| A | 10 | 7 | 31 | 34 | |
| B | 4 | 2 | 22 | 25 | |
| C | B | 7 | 4 | 43 | 47.5 |
| D | A,C | 3 | 2 | 36 | 37.5 |
| E | D | 10 | 8 | 41 | 47 |
| F | D | 8 | 6 | 30 | 38 |
| G | E | 7 | 5 | 27 | 31 |
| H | G,F | 4 | 2 | 20 | 27 |
What is the total duration of project? What is the total cost of the project under normal completion? If the project needs to be crashed for two days, which activities should be expedited? What would be the total cost of project after crashing of two days?