Question: Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 10 5000 10 5000 B
Given the following project:
| Activity | Predecessor | Normal Time (day) | Normal Cost ($) | Crash Time (day) | Crash Cost ($) |
| A | - | 10 | 5000 | 10 | 5000 |
| B | - | 12 | 1200 | 11 | 1300 |
| C | A,B | 11 | 3600 | 9 | 4800 |
| D | C | 5 | 300 | 4 | 600 |
| E | C | 8 | 1000 | 6 | 2000 |
| F | C | 9 | 2400 | 7 | 5400 |
| G | D,E,F | 8 | 700 | 7 | 1000 |
(c) Calculate the cost of the project at all time durations (decrease total duration by one day on each iteration) until you can no longer crash the project any further.
| Project Duration (day) | Total Direct Costs | |
| Normal duration |
|
|
| Normal duration -1 day |
|
|
| Normal duration -2 day |
|
|
| Normal duration -3 day |
|
|
| Normal duration -4 day |
|
|
| Normal duration -5 day |
|
|
| Normal duration -6 day |
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
