Question: Activity Predecessor Normal time Crash time Normal Cost Crash Cost S A 11 8 $2,000 3,000 $333.33 B A 9 7 2,500 3,000 $250.00 C
Activity Predecessor Normal time Crash time Normal Cost Crash Cost S A 11 8 $2,000 3,000 $333.33 B A 9 7 2,500 3,000 $250.00 C A 8 5 2,800 3,300 $166.67 D B 15 12 2,000 2,800 $266.67 E B 14 11 1950 2,450 $166.67 F C,D 12 10 2,500 2,900 $200.00 G E,F 10 8 3,300 3,800 $250.00
The inspector John Malkovich is essential for Activity F; Mr. Malkovich caught sever case of COVID 19 and had to stay in the hospital for four days and recover at home for another three working days. What is the impact of Mr. Malkovich's illness on the project?
Group of answer choices
Delay the project by 3 days
Delay the project by 7 days
Delay the project by zero days
Delay the project by 4 days