Question: Activity Predecessor Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Crash Cost per Day ($/day) A B 5 200 4 350
| Activity | Predecessor | Normal Time (days) | Normal Cost ($) | Crash Time (days) | Crash Cost ($) | Crash Cost per Day ($/day) |
| A | B | 5 | 200 | 4 | 350 | 150 |
| B |
| 8 | 220 | 8 | 220 | 0 |
| C | B | 6 | 250 | 4 | 650 | 200 |
| D | A | 9 | 500 | 5 | 600 | 25 |
| E | A, C | 10 | 150 | 9 | 500 | 350 |
| F | E | 10 | 500 | 9 | 650 | 150 |
| G | D, F | 8 | 400 | 6 | 900 | 250 |
- Create the project schedule network using normal times. List all the project paths with their normal lengths. Insert the image of the schedule below.
- Fill the Crash Cost Per Day column in the table.
- Fill the table below with the crashing information for each round of crashing. Fill it until all-crashed mode.
|
| Project Duration | Activity (ies) Crashed | Incremental Crash Cost | Cumulative Crash Cost |
| 1 |
|
|
|
|
| 2 |
|
|
|
|
| 3 |
|
|
|
|
| 4 |
|
|
|
|
| 5 |
|
|
|
|
| 6 |
|
|
|
|
| 7 |
|
|
|
|