Question: Activity Predecessor Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Crash Cost per Day ($/day) A B 5 200 4 350

Activity

Predecessor

Normal Time

(days)

Normal Cost

($)

Crash Time

(days)

Crash Cost

($)

Crash Cost per Day

($/day)

A

B

5

200

4

350

150

B

8

220

8

220

0

C

B

6

250

4

650

200

D

A

9

500

5

600

25

E

A, C

10

150

9

500

350

F

E

10

500

9

650

150

G

D, F

8

400

6

900

250

  1. Create the project schedule network using normal times. List all the project paths with their normal lengths. Insert the image of the schedule below.

  1. Fill the Crash Cost Per Day column in the table.

  1. Fill the table below with the crashing information for each round of crashing. Fill it until all-crashed mode.

Project Duration

Activity (ies) Crashed

Incremental Crash Cost

Cumulative Crash Cost

1

2

3

4

5

6

7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!