Question: Activity Predecessor Normal Time (days) Normal Cost ($) Normal Time (days) Crash Cost ($) Crash cost A B 5 200 4 350 B 8 220
| Activity | Predecessor | Normal Time (days) | Normal Cost ($) | Normal Time (days) | Crash Cost ($) | Crash cost |
| A | B | 5 | 200 | 4 | 350 |
|
| B |
| 8 | 220 | 8 | 220 |
|
| C | B | 6 | 250 | 4 | 650 |
|
| D | A | 9 | 500 | 5 | 600 |
|
| E | A, C | 10 | 150 | 9 | 500 |
|
| F | E | 10 | 500 | 9 | 650 |
|
| G | D, F | 8 | 400 | 6 | 900 |
|
Using about data,
1, Create the project schedule and determine the duration using normal times.
2, Determine the order in which you world crash the project one day, two day, and so on until the project is in all crash mode.
3, Identify how m much it will cost for each day you crash the project
| Duration | Activity (ies) | Incremental Crash Cost | Cumulative Crash Cost |
|
| <- Normal duration | ||
|
|
|
|
|