Question: Activity Predecessor Normal Time (days) Normal Cost ($) Normal Time (days) Crash Cost ($) Crash cost A B 5 200 4 350 B 8 220

Activity

Predecessor

Normal

Time

(days)

Normal

Cost

($)

Normal

Time

(days)

Crash

Cost

($)

Crash cost

A

B

5

200

4

350

B

8

220

8

220

C

B

6

250

4

650

D

A

9

500

5

600

E

A, C

10

150

9

500

F

E

10

500

9

650

G

D, F

8

400

6

900

Using about data,

1, Create the project schedule and determine the duration using normal times.

2, Determine the order in which you world crash the project one day, two day, and so on until the project is in all crash mode.

3, Identify how m much it will cost for each day you crash the project

Duration

Activity (ies)

Incremental

Crash Cost

Cumulative

Crash Cost

<- Normal duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!