Question: Activity Predecessor Optimistic ( minimum ) Most likely Pessimistic ( maximum ) A - 1 2 4 B - 5 6 7 C - 2
Activity
Predecessor
Optimistic minimum
Most likely
Pessimistic maximum
A
B
C
D
A
E
C
F
A
G
BDE
The expected duration of activity C in weeks is