Question: Activity Predecessor Optimistic ( minimum ) Most likely Pessimistic ( maximum ) A - 1 2 4 B - 5 6 7 C - 2

Activity
Predecessor
Optimistic (minimum)
Most likely
Pessimistic (maximum)
A
-
1
2
4
B
-
5
6
7
C
-
2
4
5
D
A
1
3
4
E
C
4
5
7
F
A
3
4
5
G
B,D,E
1
2
3
The expected duration of activity C in weeks is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock