Question: Activity Predecessor Optimistic (minimum) Most likely Pessimistic (maximum) A - 1 2 4 B - 5 6 7 C - 2 4 5 D A

Activity

Predecessor

Optimistic (minimum)

Most likely

Pessimistic (maximum)

A

-

1

2

4

B

-

5

6

7

C

-

2

4

5

D

A

1

3

4

E

C

4

5

7

F

A

3

4

5

G

B,D,E

1

2

3

What is the critical path?

The expected duration of the critical path in weeks is _______

What is the probabilty of not completeing this project in 12 weeks or less?

What is the probabilty of failing to finish the project in 13 weeks or less?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!