Question: Activity Predecessor Optimistic (minimum) Most likely Pessimistic (maximum) A - 1 2 4 B - 5 6 7 C - 2 4 5 D A
| Activity | Predecessor | Optimistic (minimum) | Most likely | Pessimistic (maximum) |
| A | - | 1 | 2 | 4 |
| B | - | 5 | 6 | 7 |
| C | - | 2 | 4 | 5 |
| D | A | 1 | 3 | 4 |
| E | C | 4 | 5 | 7 |
| F | A | 3 | 4 | 5 |
| G | B,D,E | 1 | 2 | 3 |
What is the critical path?
The expected duration of the critical path in weeks is _______
What is the probabilty of not completeing this project in 12 weeks or less?
What is the probabilty of failing to finish the project in 13 weeks or less?