Question: Activity Predecessor Successor Time Cost Time Cost A B,C 5 $60 2 $125 B A D C 4 4 70 N 90 C A,B D

Activity Predecessor Successor Time Cost Time

Activity Predecessor Successor Time Cost Time Cost A B,C 5 $60 2 $125 B A D C 4 4 70 N 90 C A,B D 09 6 80 3 150 D B, C --- 3 40 1 60 What is the normal project completion time, given the information above? a 11 0 13 0 14 16