Question: Activity Predecessor Time (days) Optimistic Time (days) Most likely Time (days) Pessimistic t v a - 15 18 25 b - 15 18 20 c
Activity Predecessor Time (days) Optimistic Time (days) Most likely Time (days) Pessimistic t v a - 15 18 25 b - 15 18 20 c a,b 6 10 12 d c 18 24 26 e d 13 19 25 f d 12 18 23 g d 15 17 19 h f,g 22 25 30 i e,f 11 15 17 4.1 Calculate the time (t) and variance (v) for each activity. (8) 4.2 Describe how the network diagram (AON) can be used for the information presented above. (diagram not required) (12) 4.3 Identify the paths and the critical path. (5) END OF