Question: Activity predecessor Time table [ [ A , None, 5 ] , [ B , A , 4 ] , [ C , A

Activity predecessor Time
\table[[A,None,5],[B,A,4],[C,A,7],[D,C,8],[E,B,D,10]]
a- Draw the network diagram
b-calculate the Es, EF, LS, LF and slack for all activities
c-what the critical path for this project?
D - what is minimum project complefion time?
 Activity predecessor Time \table[[A,None,5],[B,A,4],[C,A,7],[D,C,8],[E,B,D,10]] a- Draw the network diagram b-calculate the