Question: Activity predecessor Time table [ [ A , None, 5 ] , [ B , A , 4 ] , [ C , A
Activity predecessor Time
tableNone,
a Draw the network diagram
bcalculate the Es EF LS LF and slack for all activities
cwhat the critical path for this project?
D what is minimum project complefion time?