Question: Activity Predecessors Durations (days) none 2. B 3 C 4 D B 1 E B and C 3 F D and E 6 G C

Activity Predecessors Durations (days) none 2. B
Activity Predecessors Durations (days) none 2. B
Activity Predecessors Durations (days) none 2. B 3 C 4 D B 1 E B and C 3 F D and E 6 G C and D 3 For the preceding project, the earliest finish for activity F is: Seleccione una: F D and E 6 G C and D 3 3 For the preceding project, all of the following activities are critical, except: Seleccione una: . O b. F O c. E O d. D. Siguiente pgina Pgina anterior