Question: Question 21 9 pt Given the information below: Activity Immediate Predecessors Duration (days) A 5 B 6 C 3 D C 2 E A 10

 Question 21 9 pt Given the information below: Activity Immediate Predecessors

Question 21 9 pt Given the information below: Activity Immediate Predecessors Duration (days) A 5 B 6 C 3 D C 2 E A 10 F B, D 6 G C 7 a. This project will be completed in days. b. Is task A critical? (type yes or no) c. Task F has a total float of days