Question: activity predecessors normal _ time crash _ time normal _ cost crash _ cost A 5 3 4 0 0 0 8 0 0 0
activity predecessors normaltime crashtime normalcost crashcost
A
B A
C B
D C
E B
F E
The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? Only enter the name of the activity. Lower or uppercase both work. Ex: A or a Copyrighted content. Cannot be posted. orsdemir
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
