Question: activity predecessors normal _ time crash _ time normal _ cost crash _ cost A 5 3 4 0 0 0 8 0 0 0

activity predecessors normal_time crash_time normal_cost crash_cost
A 5340008000
B A 4430003000
C B 2125006000
D C 3135009500
E B 4440004000
F E 51500015000
The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? (Only enter the name of the activity. Lower or uppercase both work. Ex: A or a. Copyrighted content. Cannot be posted. orsdemir)