Question: a. Draw a project network. (No Handwritten assignments accepted) Activity Predecessor(s) Normal Time (Wks) Crash Time (Wks) Normal

a. Draw a project network. (No Handwritten assignments accepted)

       
ActivityPredecessor(s)Normal Time (Wks)Crash Time (Wks)Normal CostCrash Cost 
A ---54$400 $750  
BA8616002200 
CA768001100 
D--656001000 
EB,D,C8612002200 
FD328001000 
GD32500650 
HE43400600 
IF,G,H659001300 

b. What is the critical path?

c. What is the normal project cost?

d. What is the total cost of the project if you need to crash it by 1 week?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer To solve this problem lets first draw the project network diagram then identify the critical path calculate the normal project cost and finally ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!