Question: a. Draw a project network. (No Handwritten assignments accepted) Activity Predecessor(s) Normal Time (Wks) Crash Time (Wks) Normal
a. Draw a project network. (No Handwritten assignments accepted)
| Activity | Predecessor(s) | Normal Time (Wks) | Crash Time (Wks) | Normal Cost | Crash Cost | |
| A | --- | 5 | 4 | $400 | $750 | |
| B | A | 8 | 6 | 1600 | 2200 | |
| C | A | 7 | 6 | 800 | 1100 | |
| D | -- | 6 | 5 | 600 | 1000 | |
| E | B,D,C | 8 | 6 | 1200 | 2200 | |
| F | D | 3 | 2 | 800 | 1000 | |
| G | D | 3 | 2 | 500 | 650 | |
| H | E | 4 | 3 | 400 | 600 | |
| I | F,G,H | 6 | 5 | 900 | 1300 |
b. What is the critical path?
c. What is the normal project cost?
d. What is the total cost of the project if you need to crash it by 1 week?
Step by Step Solution
There are 3 Steps involved in it
Answer To solve this problem lets first draw the project network diagram then identify the critical path calculate the normal project cost and finally ... View full answer