Question: Activity Predecessors Times a m b A -- 4 6 8 B A 4 6 8 C A 2 4 6 D B,C 1 8
Activity Predecessors Times
a m b
A -- 4 6 8
B A 4 6 8
C A 2 4 6
D B,C 1 8 9
E D 3 5 7
F D,E 2 3 4
a.The critical path is ___.
b.expected time for project completion?
c.slack time exists for what activity?
d. the late start time for activity c?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts