Question: Activity Predecessors Times a m b A -- 4 6 8 B A 4 6 8 C A 2 4 6 D B,C 1 8

Activity Predecessors Times

a m b

A -- 4 6 8

B A 4 6 8

C A 2 4 6

D B,C 1 8 9

E D 3 5 7

F D,E 2 3 4

a.The critical path is ___.

b.expected time for project completion?

c.slack time exists for what activity?

d. the late start time for activity c?