Question: Activity Start Node Finish Node Optimistic Time Estimates ( days ) Most Likely Time Estimates ( days ) Pessimistic Time Estimates ( days ) A

Activity
Start
Node
Finish
Node
Optimistic Time
Estimates (days)
Most Likely Time
Estimates (days)
Pessimistic Time
Estimates (days)
A
1
2
11
20
29
B
2
3
2
5
8
C
2
4
18
30
42
D
3
4
7
10
13
E
1
4
31
40
43
35 weeks
39 weeks
104 weeks
105 weeks
50 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!