Question: Activity Time Predecessor A 8 B A C 5 B, F D 12 A 8 D 4. D G 9 E, F I TI C,

Activity Time Predecessor A 8 B A C 5 B, F D 12 A
Activity Time Predecessor A 8 B A C 5 B, F D 12 A
Activity Time Predecessor A 8 B A C 5 B, F D 12 A 8 D 4. D G 9 E, F I TI C, G 5 1 D Question 1 What is the earliest finish time for activity B? 8 days 32 days 0 20 days 12 days D Question 2 What is the earliest start time for activity F? 8 days 24 days 28 days 20 days