Question: Activity Time ( weeks ) Immediate Predecessor ( s ) Activity Time ( weeks ) Immediate Predecessor ( s ) A 7 minus E 4
Activity
Timeweeks
Immediate Predecessors
Activity
Timeweeks
Immediate Predecessors
A
minus
E
B
B
minus
F
B
C
A
G
C E
D
A
H
D F
Part
Daves earliest startES and earliest finishEF are:
Activity
ES
EF
A
enter your response here