Question: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 E 3 B B 7 F 5 B C 4 A G 11

Activity

Time (weeks)

Immediate Predecessor(s)

Activity

Time (weeks)

Immediate Predecessor(s)

A

7

E

3

B

B

7

F

5

B

C

4

A

G

11

C, E

D

1

A

H

8

D , F

Part 2

a. Dave's earliest start (ES) and earliest finish (EF) are:

b.Dave's earliest start (LS) and earliest finish (LF) are:

c. The slack times are:

e. The activities on the critical path are

f. the total project completion time for Dave = __ weeks.