Question: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 E 3 B B 7 F 5 B C 4 A G 11
| Activity | Time (weeks) | Immediate Predecessor(s) | Activity | Time (weeks) | Immediate Predecessor(s) |
| A | 7 | E | 3 | B | |
| B | 7 | F | 5 | B | |
| C | 4 | A | G | 11 | C, E |
| D | 1 | A | H | 8 | D , F |
Part 2
a. Dave's earliest start (ES) and earliest finish (EF) are:
b.Dave's earliest start (LS) and earliest finish (LF) are:
c. The slack times are:
e. The activities on the critical path are
f. the total project completion time for Dave = __ weeks.