Question: ActivityImmediate PredecessorOptimisticMost ProbablePessimisticA 3 5 6 B 2 4 6 CA , B 4 5 6 DA , B 6 8 9 EB 2 4
ActivityImmediate PredecessorOptimisticMost ProbablePessimisticABCA BDA BEBFCGDHD FIE G H
a
What are the critical activities? Enter your answers as a commaseparated list.
$$A DGH I
b
What is the expected time in days to complete the project? Round your answer to two decimal places.
days
c
Based only on the critical path, what is the estimated probability that the project can be completed in or fewer days?