Question: a)Draw an AON project network. b)On the AON project network, determine EST, EFT, LST, LFT, and slack for each activity. c) What are the critical

a)Draw an AON project network. b)On the AON project network, determine EST, EFT, LST, LFT, and slack for each activity. c) What are the critical path and the completion time
Activity Immediate Predecessors Normal Time (Weeks) A 32 B 28 . 36 D B 16 E B 32 F B 54 G D 17 H 20 I E, G E,G C,F 34 J 18Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts