Question: a)Draw an AON project network. b)On the AON project network, determine EST, EFT, LST, LFT, and slack for each activity. c) What are the critical

a)Draw an AON project network. b)On the AON

a)Draw an AON project network. b)On the AON project network, determine EST, EFT, LST, LFT, and slack for each activity. c) What are the critical path and the completion time

Activity Immediate Predecessors Normal Time (Weeks) A 32 B 28 . 36 D B 16 E B 32 F B 54 G D 17 H 20 I E, G E,G C,F 34 J 18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!