Afeeya Faeeqa AOR Bakery is planning to produce a new line of cake. The management has designated an output rate of 40 units per day.
Afeeya Faeeqa AOR Bakery is planning to produce a new line of cake. The management has designated an output rate of 40 units per day. The company's operations time is from 9.00 a.m. until 5.00 p.m. in a day and the productive time per hour at 55 minutes. The tasks involved are as follows:
assignment/ Task | follow/ Predecessors | Assignment Time/ Task Time (Minutes) |
A | - | 10 |
B | A | 11 |
C | B | 5 |
D | B | 4 |
AND | A | 10 |
F | C, D | 2 |
G | F | 7 |
H | AND | 11 |
I | G, H | 3 |
a) Calculate the cycle time for this operation (minutes/unit).
b) Compute the total task time (minutes).
c) Compute the theoretical minimum number of workstations
d)What is the actual number of workstations?
e) What is the largest cyle time (minutes)?
d) What is the percentage of the line efficiency?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started