Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =47, LF C = 61; activity times are A = 4, B = 6, C = 8
a. 36
b. 39
c. 41
d. Insufficient information
e. 37