Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =

An activity, A, has two succeeding activities, B
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B = 15, EF C = 17, LE B = 24, LF C = 27; activity times are A= 4, B = 6, C = 8. O a. 16 O b. 15 O c. 117 O d. 18 O e. 14