Question: An activity being analyzed under PERT was judged to most likely have a duration of 4 0 ?days. When considering the time it would take

An activity being analyzed under PERT was judged to most likely have a duration of 40 ?days. When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to be able to be doable in 20 ?days and even under the worst case imaginable, the task would be take 50 ?days. The estimates PERT duration of that activity is: