Question: An activity in a network diagram has an optimistic time estimate of 7 days, a most likely time estimate of 11 days, and a pessimistic
An activity in a network diagram has an optimistic time estimate of 7 days, a most likely time estimate of 11 days, and a pessimistic time estimate of 19 days. Its variance is _________.
a. 6
b. 2
c. 4
d. 12
e. 24