Question: An activity on a PERT network has these time estimates: optimistic = 1.6, most likely = 5.4, and pessimistic = 10. What is its expected
An activity on a PERT network has these time estimates: optimistic =
1.6,
most likely =
5.4,
and pessimistic = 10. What is its expected activity time and
variance?
(Do not round intermediate calculations. The round final answer to two decimal places.)