Question: An activity on a PERT network has these time estimates: optimistic = 1.6, most likely = 5.4, and pessimistic = 10. What is its expected

An activity on a PERT network has these time estimates: optimistic =

1.6,

most likely =

5.4,

and pessimistic = 10. What is its expected activity time and

variance?

(Do not round intermediate calculations. The round final answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!