Question: An activity on a PERT network has these time estimates: optimistic = 1 , most likely = 4 . 5 , and pessimistic = 1
An activity on a PERT network has these time estimates: optimistic most likely and pessimistic What is its expected activity time and varianceDo not round intermediate calculations. Round final answer to two decimal places.