Question: An activity on a PERT network has these time estimates: optimistic = 2 , most likely = 5 , and pessimistic = 1 0 .

An activity on a PERT network has these time estimates: optimistic =2, most likely =5, and pessimistic =10. Its expected time is
Group of answer choices
5
5.33
5.67
17
None

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!