Question: An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 9. Its expected time and
An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 9. Its expected time and variance (if it is a critical activity) are
- A. 4.3; 1.5.
- B. 3.6; 0.8.
- C. 2.5; 1.4.
- D. 5.3; 1.
- E. 3.3; 0.5.