Question: An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 9. Its expected time and

An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 9. Its expected time and variance (if it is a critical activity) are

  • A. 4.3; 1.5.
  • B. 3.6; 0.8.
  • C. 2.5; 1.4.
  • D. 5.3; 1.
  • E. 3.3; 0.5.