Question: An activity on a PERT network has these time estimates: optimistic = 11, most likely = 16, and pessimistic = 24. What is its expected
An activity on a PERT network has these time estimates: optimistic =
11,
most likely =
16,
and pessimistic = 24. What is its expected activity time? (Do not round intermediate calculations. Round final answer to two decimal places.)
A.
17.50
B.
6.50
C.
16.50
D.
21.00
E.
25.50
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
