Question: Q12: An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 10. Its expected time
Q12:
An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 10. Its expected time is
a.
5.5
b.
5
c.
5.33
d.
5.67
e.
18