Question: An Agile project is in progress. This project was broken down into functions and features leading to 156 story points. The project is planned for

An Agile project is in progress. This project was broken down into functions and features leading to 156 story points. The project is planned for 12 sprints and a budget of $2250000. If the project did achieve 78 points during the first 8 sprint, the Earned Value is:

a) 1250,000

b)1125,000

c)150,000

d)1750000