Question: QUESTION 18 An Agile project is in progress. This project was broken down into functions and features leading to 1500 story points. The project is
QUESTION 18
-
An Agile project is in progress. This project was broken down into functions and features leading to 1500 story points. The project is planned for 10 sprints of 4 weeks each and a budget of $2250000. If the project did achieve 750 points during the first 8 sprint, what is the forecast/estimated duration of project?
one year
one and a half year
two years
One year and 4 months