Question: QUESTION 18 An Agile project is in progress. This project was broken down into functions and features leading to 1500 story points. The project is

QUESTION 18

  1. An Agile project is in progress. This project was broken down into functions and features leading to 1500 story points. The project is planned for 10 sprints of 4 weeks each and a budget of $2250000. If the project did achieve 750 points during the first 8 sprint, what is the forecast/estimated duration of project?

    one year

    one and a half year

    two years

    One year and 4 months