Question: QUESTION 12 An Agile project is in progress. This project was broken down into functions and features leading to 150 story points. The project is

QUESTION 12

  1. An Agile project is in progress. This project was broken down into functions and features leading to 150 story points. The project is planned for 12 sprints and a budget of $2250000. If the project did achieve 75 points during the first 8 sprint, the Earned Value is:

    1250,000

    1125,000

    150,000

    1750000