Question: An Agile project is in progress. This project was broken down into functions and features leading to 150 story points. The project is planned for
An Agile project is in progress. This project was broken down into functions and features leading to 150 story points. The project is planned for 10 sprints of 4 weeks each and a budget of $2250000. If the project did achieve 75 points during the first 8 sprint, what is the forecast/estimated duration of project? one year one and a half year two years 16 Months or 64 week