Question: An assembly line with 1 0 tasks is to be balanced. The longest task is 3 minutes, and the total time for all tasks is

An assembly line with 10 tasks is to be balanced. The longest task is 3 minutes, and the total time for all tasks is 20 minutes. The cycle time is 5 minutes, there are 5 stations and total idle time is 3. What is the efficiency?
Cevap seenekleri grubu
88%
50%
75%
100%