Question: Answer : ( c ) Precedence Network Diagram with forword and backword pass computation: - Es Acc Ef Ls Dur Lf 0 a 0 .

Answer :
(c)
Precedence Network Diagram with forword and backword pass computation:-
Es Acc Ef
Ls Dur Lf
0 a 0.2
00.20.2
X
0.2 b 0.6
0.40.40.8
0.2 e 1.2
01.01.2
0.6 c 1.1
0.80.51.3
1.2 f 1.7
1.20.51.7
Critical Path : a--e--f--g--i--k--l--m--n
Porject duration(Cycle Time)=6.7 Minutse
(a)
Total Available Time per shift =8 Hrs -(10*2+40) Min =8 Hrs -60 Min =7 Hrs =7*60 Min =420 Min
The number of widgets that can be produced per shift with one workstation= Total Available Time / Cycle time =420/6.7=62.68=63 Widgets
Hence, it is not possible to accomplish the objective of 300 widgets per shift with one workstation.
(b)
Maximum possible output with 14 workstation =63*14=883 Widgets
(d)
Theoretical minimum number of workstations to achieve 300 pieces per shift =300/63=4.76=5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!