Question: Answer the following: 1. The project completion time = Answer days 2. Labor resources needed in in the following intervals of time ( day(s) ):
Answer the following:
1. The project completion time = Answer days
2. Labor resources needed in in the following intervals of time ( day(s) ):
[0-1] = Answer
[1-2] = Answer
[2-3] = Answer
[3-4] = Answer
[4-5] = Answer
[5-6] = Answer
[6-9] = Answer
[9-12] = Answer
3. The peak demanding period of labor is Answer[2-3][3-4][4-5][5-6][6-9]
Activity A B D E F G H Consider the following data about a project: Duration Predecessor Labor in days Requirement 2 3 1 2 3 5 2 3 4 B 2 3 7 2 DE 4 3 F,G 2 NON 2