Question: Answer the questions for this project: Activity Expected Duration Predecessors A 4 days B 9 days A C 11 days A D 5 days B
Answer the questions for this project:
| Activity | Expected Duration | Predecessors |
| A | 4 days | |
| B | 9 days | A |
| C | 11 days | A |
| D | 5 days | B |
| E | 3 days | B |
| F | 7 days | C |
| G | 3 days | D, F |
| H | 2 days | E, G |
| I | 1 day | H |
- Create a Gantt chart out of the network.
- What is the critical path? Which activities have slack time?
- What would happen if activities B and D took 5 more days to complete than was anticipated? The critical path would change in what way?