Question: Answer the questionusing the work breakdown structure(WBS)shown below(numbers in parentheses show the dollar value for a particular element): 1.00.00 1.1.0 ($25K) 1.1.1 1.1.2 ($12K) 1.2.0

Answer the questionusing the work breakdown structure(WBS)shown below(numbers in parentheses show the dollar value for a particular element):

  • 1.00.00
    • 1.1.0
($25K)
      • 1.1.1
      • 1.1.2
($12K)
    • 1.2.0
      • 1.2.1
($16K)
      • 1.2.2.0
        • 1.2.2.1
($20K)
        • 1.2.2.2
($30K)

The cost of the entire program (1.00.00) is:

$25K
$66K
$91K
Cannot be determined