Question: Question 1. In the following work breakdown structure (WBS), the numbers in parentheses show the dollar value for a particular element: 1. ($50K) ($24K) 1.1.

Question 1. In the following work breakdown

Question 1. In the following work breakdown structure (WBS), the numbers in parentheses show the dollar value for a particular element: 1. ($50K) ($24K) 1.1. 1.1.1. 1.1.2. 1.2. 1.2.1. 1.2.2. 1.2.2.1. 1.2.2.2. ($32K) ($40K) ($60K) Use the above WBS to answer the following questions. a) What is the cost of WBS element 1.2.2.? Can it be determined? b) What is the cost of WBS element 1.1.1.? Can it be determined? c) What is the cost of the entire project (1.)? Can it be determined