Question: Applejack Construction is contracted to build a freeway for $12,000,000. Construction began in 2020 and was completed in 2021. Data relating to the construction are
Applejack Construction is contracted to build a freeway for $12,000,000. Construction began in 2020 and was completed in 2021. Data relating to the construction are shown below.
| 2020 | 2021 | ||
| Costs incurred during the year | $ 3,500,000.00 | $ 3,250,000.00 | |
| Estimated costs to complete | $ 2,500,000.00 | ||
| Using the percentage-of-completion method, answer the below questions. | |||
1. How much revenue should be reported for 2020? Show your computation.
2. Make the entry to record progress billings of $4,900,000 during 2020.
3. Make the entry to record the revenue and gross profit for 2020.
4. How much gross profit should be reported for 2021? Show your computation.
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
To determine the revenue to be reported for 2020 using the percentageofcompletion method we need to ... View full answer
Get step-by-step solutions from verified subject matter experts