Question: As part of a mid - project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?
A.
Work Breakdown Strycture (WBS)
B.
Estimate at Completion (EAC)
C.
Budget at Completion (BAC)
D.
Estimate to Completion (ETC)