Question: ASAP! Manage Prod 2 please help Given is a Project with network diagram and activity times as shown below. a) The Earliest Start (ES) time

Given is a Project with network diagram and activity times as shown below. a) The Earliest Start (ES) time of Activity I = Blank 1 weeks b) The Latest Start (LS) time of Activity B = Blank 2 weeks c) The Slack time of Activity C= Blank 3 weeks d) The Earliest Finish (EF) time of Activity H= Blank 4 weeks a) The Earliest Start (ES) time of Activity I= Blank 1 weeks b) The Latest Start (LS) time of Activity B = Blank 2 weeks c) The Slack time of Activity C= Blank 3 weeks d) The Earliest Finish (EF) time of Activity H= Blank 4 weeks e) The Latest Finish (LF) time of Activity B= Blank 5 weeks f) The Project Completion time = Blank 6 weeks