Question: Given is a Project with network diagram and activity times as shown below. H Start H Activity Time (wks) 10 B 5 IC 16 D

Given is a Project with network diagram and
Given is a Project with network diagram and
Given is a Project with network diagram and activity times as shown below. H Start H Activity Time (wks) 10 B 5 IC 16 D 16 E 3 F 15 G 12 a) The Earliest Start (ES) time of Activity I = weeks b) The Latest Start (LS) time of Activity B = weeks Weeks c) The Slack time of Activity C = d) The Earliest Finish (EF) time of Activity H= weeks e) The Latest Finish (LF) time of Activity B = weeks f) The Project Completion time = weeks