Question: Given is a Project with network diagram and activity times as shown below. Activity A B C D E F G H I J Time
-
Given is a Project with network diagram and activity times as shown below.
Activity
A
B
C
D
E
F
G
H
I
J
Time (wks)
2
3
14
11
9
3
2
8
3
2
a) The Earliest Start (ES) time of Activity I = Blank 1 weeks
b) The Latest Start (LS) time of Activity B = Blank 2 weeks
c) The Slack time of Activity C = Blank 3 weeks
d) The Earliest Finish (EF) time of Activity H = Blank 4 weeks
e) The Latest Finish (LF) time of Activity B = Blank 5 weeks
f) The Project Completion time = Blank 6 weeks